We will be testing the battery Phase II and IIII next week from April 22-25. (Dates TBD)
These are the following tests that need to be completed:
- Test 1 -Battery with more power resistors + the e stop (to simulate 4 motors)
- Test 2 - Battery with the motors unloaded
- Test 3 - Battery with motors loaded
- Test 4 - Integrated Battery Tests (Suit simulation - pi collecting data, + controlling motors)
The "Integrated Battery Testing Documentation" document has been added to Teams -> Power -> Testing -> Battery Testing and outlinines the 4 battery tests that need to be done.
Motors
- Please add notes to Test 2 and 3, to help develop a testing plan ahead of April 23.
Safety
- Please add Safety considerations to these tests ahead of April 23.
DEADLINE: April 22
This will help things run a lot more efficeintly when we are in person to test. We understand it's exam season so whenever you have the time to work on it within the upcoming days that would be very helpful.