roof above the tunnel is leaking #12

Closed
5 of 8 tasks
msimerson opened this issue Nov 6, 2019 · 3 comments
Closed
5 of 8 tasks

roof above the tunnel is leaking #12

msimerson opened this issue Nov 6, 2019 · 3 comments
Assignees
Labels
buildings Meany lodge permanent structures

Comments

@msimerson
Copy link
Contributor

msimerson commented Nov 6, 2019

@msimerson msimerson added the buildings Meany lodge permanent structures label Nov 6, 2019
@msimerson
Copy link
Contributor Author

msimerson commented Sep 7, 2021

tearoff (2021-08-14)

Tunnel Dismantling 8 14 21

repairing all sources of decay

IMG_3059

@msimerson msimerson self-assigned this Sep 7, 2021
@msimerson
Copy link
Contributor Author

Starting the Walls

IMG_3129

Walls up

IMG_3148

Deck laid and rails up

IMG_3234

@msimerson
Copy link
Contributor Author

msimerson commented Dec 8, 2021

Meany Lodge Porch Assembly

  • Stairs
    • Set the pier blocks
      • Level the soil around the stairs area
      • Dig holes
      • fill base of holes with pea gravel
    • Construct the landing
      • stairs are 7-1/2 x 10-1/4" so 37.5" below deck height
  • Deck Rails
    • Order Flashing / flashing / drip edge from B&D
    • install fascia
    • mount deck rail posts
      • cut custom blocks for 4x4 posts
      • (7) cut railing posts to 54"
      • add 2x10" blocking for post bolts
      • affix 3/8" threaded rod through the blocking
  • Odds and Ends
    • Cut 12' decking down to size
    • mortar in top course of pillars
      • fill with concrete
      • set the post anchors
    • make forms for steps at end of tunnel
      • pour tunnel steps
    • pour cores below glass blocks
    • dig french drain along footing
      • line with landscaping fabric
      • fill with peat gravel
      • tie into existing dry well
    • Bear weight of fire escape to …
    • hang the last outer joist
    • Measure stair tread length, 40”
    • mortar all gaps and cracks in the tunnel wall
  • Decking
    • lay starter strip at South edge of deck
    • proceed across the deck
  • Deck framing
    • install insect screen between joists & purlins
    • trim joists to length
    • cover joists with flashing tape
    • lay purlins perpendicular to the joists
    • TODO: acquire
      • ledger bolts
        • 1/2" hot dipped galvanized bolts & nuts, max 29" on center
        • Simpson SDWS, max 8" on center
      • framing lumber
        • 2x4x8' (38)
        • 2x6x8' (2)
        • 2x8x8' (2)
        • 2x10x8' (19)
        • 2x10x12' (2)
        • 2x8x10' (2)
        • 2x10x10' (7)
      • insect screening
      • hurricane ties
      • joist hangers
    • install sills on J-bolts
    • attach ledgers to the lodge
    • affix joist hangars to the ledger
    • lay the joists
    • affix joists to sill with hurricane ties
  • Walls
    • Lay remaining courses of blocks
    • Cut (8) pieces of 1/2" rebar 3' long
    • Cut (37) pieces of 1/2" rebar 2' long
    • Fill cores with rebar per schedule
    • Fill cores of wall with concrete
    • Add rebar to bonded beam
    • Lay out lines for block wall perimeter
    • lay out doors & wall interior
    • Install & brace door jambs
    • cut or bend straps into door anchors
    • Lay first course of blocks
      • plumb, level, and square
      • mark inside of blocks where rebar will go
    • Lay next 5 courses of blocks
    • Wait 5-6 hours
    • TODO: acquire and deliver
      • ladder reinforcing
      • masonry door anchors?
      • cement blocks
        • 8x8x8 std (58)
        • 8x8x6 std (16)
        • 8x8x16 bond beam (65)
        • 8x8x16 split face (90)
        • 8x8x16 std (225)
      • (2) door jambs
      • sacks of concrete (115) 80# to fill block cores (95 cu ft)
      • sacks of type S mortar (34) 80#
      • 3" x 3" angle iron $84
    • Cut (46) pieces of 1/2" rebar 7' long
  • Footings
    • tie rebar elbows into 1st course of blocks
    • Pour
      • TODO: acquire and deliver
        • steel fire doors
        • cement mixer
        • 65 ft/3 of cement (110) 80#
      • around new tunnel drain
      • footings
    • tie all rebar in footing
    • drill holes in existing slabs for rebar tie-in
    • dig footings
    • build forms
    • brace & remove fire escape post
    • TODO: acquire
      • rebar (12) of 5/8", (32) 1/2"
      • (3) 12" bolts for post bracing
      • buy drain & pipe
      • form stakes
      • pea gravel
    • rent concrete saw
    • cut out block of tunnel floor for drain
    • dig out drain for tunnel
    • remove 1/2 existing porch slab
    • bust out existing concrete blocks
    • cut off any existing rebar not in the right spot

Tools from Matt's Garage

  • line level
  • Rotohammer
  • 1/2" SDS concrete bit
  • laser level

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment
Labels
buildings Meany lodge permanent structures
Projects
None yet
Development

No branches or pull requests

1 participant