One week in advance:
-
Announce on the upcoming release on all the developer mailing lists and in the IRC channel topics.
-
Include a list of projects on Jenkins that are yellow or red.
- Daily remind the lead of any project that is red.
-
For a CR/Final, also mention the FindBugs reports on Jenkins.
-
-
All external dependencies must be on a non-SNAPSHOT version, to avoid failing to close the staging repo on nexus near the end of the release.
- Get those dependencies (errai) released if needed, preferably 1 week before the kie release. This way, those released artifacts gets tested by our tests.
-
Ask kie-wb module (kie-uberfire-extensions, uberfire, kie-wb-common, drools-wb, jbpm-wb, jbpm-designer, optaplanner-wb and kie-wb-distributions) leads to update the translations with Zanata:
-
Translations into different locales are handled within Zanata (https://vendors.zanata.redhat.com)
-
Email Zanata mailing list that a release is about to be made.
-
The most recent translations need to be pulled into the release branch. Assuming you have set-up your Zanata configuration correctly, this can be achieved with:
$ mvn zanata:pull-module
-
NOTE: If releasing a new version number (major, minor or micro) a new version of the translations should be setup in Zanata.
-
Automatically fix simple errors in the translations using the following:
$ mvn replacer:replace -N
-
NOTE: For the repositories kie-wb-distributions it has to be added to the workflow
$ mvn native2ascii:native2ascii
-
NOTE: jbpm-designer has it's own workflow
$ cd ../jbpm-designer $ mvn zanata:pull-module $ mvn replacer:replace-N $ mvn native2ascii:native2ascii $ cd jbpm-designer-api $ mvn replacer:replace-N
-
Zanata workflow is:
$ mvn zanata:pull-module $ mvn replacer:replace-N $ mvn native2ascii:native2ascii # In repositories where this has to be executed, please # pay attention to jbpm-designer. $ mvn clean install -Dfull -DskipTests # To see if everything compiles after Zanata changes were pulled. # In kie-wb-distribution has to be added -Dcustom-container for preventing # not building the repo cause possibly hanging at kie-smoke-tests $ git commit -a # add & commit the changes $ git push <upstream> <branch> # push changes to blessed repository
-
-
Since Zanata translations was outsourced it have to be clafirfied before a release if the Zanata translations will be needed. (mvn -B zanata:pull-module).
-
Get access to
filemgmt.jboss.org
-
Create an SSH key (if not already done)
-
Key must:
- be RSA-2 (default for many keygen apps)
- have 1024+ bit (2048 is preferred)
- have comment with user email address
-
Using many keygen tools the following command will work
$ ssh-keygen -C your@email.com -b 2048
- enter key name
- enter passcode you want
-
Send ticket to IT
- Have it forwarded to https://engineering.redhat.com/rt/Ticket/Create.html?Queue=58 (RT3 eng-ops-mw) queue
- Specify that you would like access to drools@filemgmt.jboss.org
- Attach the *.pub that you created above
-
-
48 hours in advance:
-
Push deadline: Announce on the upcoming push deadline on all the developer mailing lists and in the IRC channel topics.
- Commits pushed before the deadline will make the release, the rest won't.
-
Pull the latest changes.
$ git-all.sh pull --rebase
-
Do a sanity check.
-
Produce the distribution zips, build with
-Dfull
:$ droolsjbpm-build-bootstrap/script/mvn-all.sh clean install -Dfull -Dcustom-container -DskipTests
-
Warning: It is not uncommon to run out of either PermGen space or Heap Space. The following settings are known (@Sept-2012) to work:-
$ export MAVEN_OPTS='-Xms512m -Xmx2200m -XX:MaxPermSize=512m'
-
Warning: Verify that workspace contains no uncommitted changes or rogue module directories of older branches:
$ droolsjbpm-build-bootstrap/script/git-all.sh status
-
Specifically watch out for an uncommitted
*/target
directory: that's the result of a build of an older branch that didn't get cleaned.- If the root of that directory gets zipped, binaries of that older branch leak into today's distribution zip.
-
-
-
Do a sanity check of the artifacts by running each runExamples.sh from the zips.
-
Go to
kie-wb-distributions/droolsjbpm-uber-distribution/target/*/download_jboss_org
:-
Unzip the zips to a temporary directory.
-
Start the
runExamples.sh
script for drools, droolsjbpm-integration and optaplanner -
Deploy the guvnor WildFly 8 war and surf to it:
- Install the mortgages examples, build it and run the test scenario's
-
Verify that the reference manuals open in a browser (HTML) and Adobe Reader (PDF).
-
-
-
A new branch name should always end with .x
so it looks different from a tag name and a topic branch name.
-
When do we create a new branch?
-
We only create a new branch just before releasing CR1.
-
For example, just before releasing 6.5.0.CR1, we created the release branch 6.5.x
- The new branch 6.2.x contained the releases 6.5.0.CR1, 6.5.0.Final, 6.5.1-SNAPSHOT, ...
-
-
Alpha/Beta releases are released directly from master, because we don't backport commits to Alpha/Beta's.
-
-
Alert the IRC dev channels that you're going to branch master.
-
Pull the latest changes.
$ git-all.sh pull --rebase
-
Create a new branch using the script kie-createNewBranches.sh:
$ ./droolsjbpm-build-bootstrap/script/release/kie-createNewBranch.sh <new branch>
- Note: this script creates a new branch, pushes it to origin and sets the upstream from local new branch to remote new branch
-
Switch back and forth from master to the new branches for all git repositories
-
If you haven't made the branches yourself, first make sure your local repository knows about them:
$ droolsjbpm-build-bootstrap/script/git-all.sh fetch
-
Switch to master with
script/git-checkout-all.sh
$ droolsjbpm-build-bootstrap/script/git-checkout-all.sh <new branch>
-
Update master to the next SNAPSHOT version to avoid clashing the artifacts on nexus of master and the release branch:
$ droolsjbpm-build-bootstrap/script/release/update-version-all.sh 7.6.1-SNAPSHOT 2.2.1-SNAPSHOT
-
Note: the arguments are
kie Version
uberfire Version
-
WARNING: script update-version-all.sh did not update all versions in all modules for 7.6.0-SNAPSHOT. Check all have been updated with the following and re-run if required.
$ grep -r '7.6.0-SNAPSHOT' **/pom.xml # or $ for i in $(find . -name "pom.xml"); do grep '7.6.0-SNAPSHOT' $i; done
or
$ grep -ER --exclude-dir=*git* --exclude-dir=*target* --exclude-dir=*idea* --exclude=*ipr --exclude=*iws --exclude=*iml --exclude=workspace* --exclude-dir=*.errai 6.3.0-SNAPSHOT . | grep -v ./kie-wb-distributions/kie-eap-integration/kie-eap-modules/kie-jboss-eap-base-modules
-
Note: in either case it is important to search for
-SNAPSHOT
, as there are various hidden-SNAPSHOT
dependencies in some pom.xml files and they should be prevented for releases -
Commit those changes (so you can tag them properly):
-
Add changes from untracked files if there are any. WARNING: DO NOT USE
git add .
. You may accidentally add files that are not meant to be added into git.$ git add {filename}
-
Commit all changes
$ droolsjbpm-build-bootstrap/script/git-all.sh commit -m "Set release version: 6.3.0-SNAPSHOT"
-
Check if all repositories build after version upgrade
$ sh droolsjbpm-build-bootstrap/mvnall.sh mvn clean install -Dfull -DskipTests
-
-
-
Push the new
-SNAPSHOT
version tomaster
of the blessed directory$ sh droolsjbpbm-build-bootstrap/script/git-all.sh pull --rebase origin master (pulls all changes for master that could be commited in the meantime and prevents merge problems when pushing commits) $ sh droolsjbpm-build-bootstrap/script/git-all.sh push origin master (pushes all commits to master)
-
Switch back to the release branch name with
script/git-checkout-all.sh
with drools and jbpm release branch name:$ sh droolsjbpm-build-bootstrap/script/git-checkout-all.sh 7.6.x
-
-
Push the created release branches to the blessed directory
$ sh droolsjbm-build-bootstrap/script/git-all.sh push origin 7.6.x
-
Set up Jenkins build jobs for the new branch.
-
Add a new branch to kiegroup/kie-jenkins-jobs
-
Edit the jobs and do the needed adaptations for the new branch
-
Note:since all these Jenkins Jobs are done with a DSL Plugin there are two things that should be done so all jobs are available:
-
the file branch-mapping.yaml should be upgraded to the new branch
-
the Jenkins Jobs
https://kie-jenkins.rhev-ci-vms.eng.rdu2.redhat.com/view/DSL/job/DSL-KIE-releases-master/
https://kie-jenkins.rhev-ci-vms.eng.rdu2.redhat.com/view/DSL/job/DSL-kieAllBuild-FlowJob-master/
https://kie-jenkins.rhev-ci-vms.eng.rdu2.redhat.com/view/DSL/job/DSL-seed-job-master/
should be updated to the new branch
-
-
-
Set up a new Jenkins view for the related release builds
-
https://jenkins.mw.lab.eng.bos.redhat.com/hudson/me/my-views/view/All/ (i.e. 7.5.x)
- Note: Add kie jobs manually or use a regex pattern similar to
^((kie).*7).*$
- Note: Add kie jobs manually or use a regex pattern similar to
-
-
Alert the dev mailing list and the IRC channel that the branch has been made.
- Remind everyone clearly that every new commit to
master
will not make the upcoming CR and Final release, unless they cherry-pick it to this new branch.
- Remind everyone clearly that every new commit to
- at this point we have created a release branch
- we have updated the master branch to the new development version (
*-SNAPSHOT
) - we have pushed the created release branches to origin
- we have set up a new Jenkins view for the created "release branch"
-
Alert the IRC dev channels that you're starting the release.
-
Pull the latest changes of the branch that will be the base for the release (branchName == master or i.e. 7.6.x)
$ git-all.sh checkout <branchName> $ git-all.sh pull --rebase
-
Create a local release branch
Name should begin with r, i.e if the release will be 7.6.0.Final the name should be r7.6.0.Final (localReleaseBranchName == r7.6.0.Final)
$ git-all.sh checkout -b <localReleaseBranchName> <branchname>
-
Check if everything builds after the last pull & execute all unit tests
$ mvn-all.sh clean install -Dfull -Dmaven.test.failure.ignore=true > testResult.txt # This will execute the build and execute the unit tests and write all logs into testResult.txt.
-
Explore testResult.txt to see if the build breaks or which unit tests are failing.
-
Mail to leads of projects the failed unit tests.
-
Do another sanity check.
If everything is perfect (compiles, Jenkins is all blue, sanity checks succeed and there is nothing to do about the failed unit tests):
-
Define the version and adjust the sources accordingly:
-
First define the version.
-
There are only 4 acceptable patterns:
-
major.minor.micro.Alpha[n]
, for example1.2.3.Alpha1
-
major.minor.micro.Beta[n]
, for example1.2.3.Beta1
-
major.minor.micro.CR[n]
, for example1.2.3.CR1
-
major.minor.micro.Final
, for example1.2.3.Final
-
-
See the JBoss version conventions
- Not following those, for example
1.2.3
or1.2.3.M1
results in OSGi eclipse updatesite corruption.
- Not following those, for example
-
The version has 3 numbers and qualifier. The qualifier is case-sensitive and starts with a capital.
- Use the exact same version everywhere (especially in URL's).
-
-
Adjust the version in the poms, manifests and other eclipse stuff.
$ droolsjbpm-build-bootstrap/script/release/update-version-all.sh 6.2.0-SNAPSHOT 6.2.0.Final
-
Note: the arguments are
releaseOldVersion releaseNewVersion
-
WARNING: FIXME the update-version-all script does not work correctly if you are releasing a hotfix version.
-
WARNING: Guvnor has a hard-coded version number in org.drools.guvnor.server.test.GuvnorIntegrationTest.createDeployment. This must be changed manually and committed.
-
WARNING: script update-version-all.sh did not update automatically all versions in all modules. Check all have been updated with the following and re-run if required.
$ grep -r '6.2.0-SNAPSHOT' **/pom.xml # or for i in $(find . -name "pom.xml"); do grep '6.2.0-SNAPSHOT' $i; done
OR
$ grep -ER --exclude-dir=*git* --exclude-dir=*target* --exclude-dir=*idea* --exclude=*ipr --exclude=*iws --exclude=*iml --exclude=workspace* --exclude-dir=*.errai 6.3.0-SNAPSHOT . | grep -v ./kie-wb-distributions/kie-eap-integration/kie-eap-modules/kie-jboss-eap-base-modules.
-
-
versions that have to be changed manually
NOTE: in droolsjbpm-build-bootstrap pom.xml there are some properties where you should pay attention to:
-
jboss-ip bom version (https://github.com/kiegroup/droolsjbpm-build-bootstrap/blob/master/pom.xml#L11) the version of jboss-integration-platform-bom. should be the most recent version released in jboss-ip-bom
-
org.kie version (https://github.com/kiegroup/droolsjbpm-build-bootstrap/blob/master/pom.xml#L48) org.kie version sometimes has to be changed manually, if needed, should be updated to release version
-
uberfire version (https://github.com/kiegroup/droolsjbpm-build-bootstrap/blob/master/pom.xml#L53) the uberfire version has to be updated manually to the last released version
-
errai version (https://github.com/kiegroup/droolsjbpm-build-bootstrap/blob/master/pom.xml#L99) the errai version has to be updated manually to the last released version
-
-
Commit those changes (so you can tag them properly):
-
Add changes from untracked files if there are any. WARNING: DO NOT USE
git add .
. You may accidentally add files that are not meant to be added into git.$ git add {filename}
-
Commit all changes
$ droolsjbpm-build-bootstrap/script/git-all.sh commit -m "Set release version: 6.2.0.Final"
-
Adjust the property
<latestReleasedVersionFromThisBranch>
in droolsjbpm-build-bootstrap/pom.xml
This should be the version that will be released now. This is important as productisation takes this version to define theirs.
- Add this change
- Commit this change.
-
-
-
Push release branches to github repository
The release branches rX.X.X.Y should be pushed to the github repository (community=kiegroup/... or product=jboss-integration/...), so the branch is available for all future steps. People can access it to review, if all commits that should be in the release were commited.
This branch has to be removed when doing the next release as a new branch starting with "r" will be pushed and we want prevent having a bunch of "obsolete" release branches. -
Create the tag locally. The arguments are the Drools version, the jBPM version:
$ droolsjbpm-build-bootstrap/script/release/git-tag-locally-all.sh 6.2.0.Final 6.2.0.Final
-
Go to nexus, menu item Staging repositories, drop all your old staging repositories.
-
Deploy the artifacts:
./droolsjbpm-build-bootstrap/script/mvn-all.sh -B -e -U clean deploy -Dfull -Drelease -T2 -Dmaven.test.failure.ignore=true -Dgwt.memory.settings="-Xmx4g -Xms1g -Xss1M" -Dgwt.compiler.localWorkers=2
-
Note: add this parameter -Dproductized if this is a release/tag for prod
-
This will take a long while (3+ hours)
-
If it fails for any reason, go to nexus and drop your stating repositories again and start over.
-
-
Go to nexus, menu item Staging repositories, find your staging repository.
-
Look at the files in the repository.
- Sometimes they are split into 2 staging repositories (with no intersecting files): just threat those 2 as 1 staging repository.
-
Button close
- This will validate the nexus rules. If any fail: fix the issues, and force a git retag locally.
-
-
Do another sanity check of the artifacts by running the examples and opening the manuals from the zips. See above.
-
This is the point of no return.
-
Warning: The slightest change after this requires the use of the next version number!
-
NEVER TAG OR DEPLOY A VERSION THAT ALREADY EXISTS AS A PUSHED TAG OR A DEPLOY!!!
-
Except deploying
SNAPSHOT
versions. -
Git tags are cached on developer machines forever and are never refreshed.
-
Maven non-snapshot versions are cached on developer machines and proxies forever and are never refreshed.
-
-
So even if the release is broken, do not reuse the same version number! Create a hotfix version.
-
-
-
Define the next development version an adjust the sources accordingly:
-
Checkout to the master-branch or the branch which is the base for this release.
$ git-all.sh checkout master (or base release branch i.e. 6.2.x)
-
Define the next development version on the branch from which you are releasing.
-
There are only 1 acceptable pattern:
major.minor.micro-SNAPSHOT
, for example1.2.0-SNAPSHOT
or1.2.1-SNAPSHOT
-
Warning: The release branch should never have the same SNAPSHOT version as any other branch.
- If you're releasing a Final, increment the micro number, not the minor number.
-
-
Adjust the version in the poms, manifests and other eclipse stuff:
$ droolsjbpm-build-bootstrap/script/release/update-version-all.sh 6.2.0.Final 6.3.0-SNAPSHOT 6.2.0.Final 6.3.0-SNAPSHOT
-
Commit those changes:
$ droolsjbpm-build-bootstrap/script/git-all.sh add . $ droolsjbpm-build-bootstrap/script/git-all.sh commit -m "Set next development version: 6.3.0-SNAPSHOT"
-
Push all changes to the blessed repository:
$ droolsjbpm-build-bootstrap/script/git-all.sh push
-
Warning: Guvnor has a hard-coded version number in org.drools.guvnor.server.test.GuvnorIntegrationTest.createDeployment. This must be changed manually and committed.
-
Warning: script update-version-all.sh did not update all versions in all modules for 6.2.0.Final. Check all have been updated with the following and re-run if required.
$ grep -r '6.2.0-SNAPSHOT' **/pom.xml # or for i in $(find . -name "pom.xml"); do grep '6.2.0-SNAPSHOT' $i; done
-
Warning: If releasing from master (i.e. a Beta release) and the push fails as there have been other commits to the remote master branch it might be necessary to pull.
$ droolsjbpm-build-bootstrap/script/git-all.sh pull
-
-
Checkout back to your local release branch.
$ git-all.sh checkout r6.2.0.Final
-
-
Push the local tag from the local release branch to the remote blessed repository.
$ droolsjbpm-build-bootstrap/script/release/git-push-tag-all.sh 6.2.0.Final 6.2.0.Final
-
Push your changes to the release branch:
-
Especially if the release branch is master: First pull any latest changes without
--rebase
, .$ git-all.sh pull
- Without the
--rebase
it's a merge, and their commits will not be rebased before your version-changing commits.
- Without the
-
Push your version-changing commits to the release branch:
$ git-all.sh push origin 5.2.x
-
-
-
Release your staging repository on Nexus
- Button release
-
Go to JIRA and for each of our JIRA projects (DROOLS, PLANNER, JBPM, GUVNOR):
-
Open menu item Administration, link Manage versions, release the version.
-
Create a new version if needed. There should be at least 2 unreleased non-FUTURE versions.
-
-
Upload the zips, documentation and javadocs to filemgmt and update the website.
-
Go to
kie-wb-distributions/droolsjbpm-uber-distribution/target
. -
To get access to
filemgmt.jboss.org
, see preparation above. -
Folder
download_jboss_org
should be uploaded tofilemgmt.jboss.org/downloads_htdocs/drools/release
which ends up at download.jboss.org- Update the download webpage accordingly.
-
Folder
docs_jboss_org
should be uploaded tofilemgmt.jboss.org/docs_htdocs/drools/release
which ends up at docs.jboss.org- Use
documentation_table.txt
to update the documentation webpage.
- Use
-
-
Update the symbolic links
latest
andlatestFinal
links on filemgmt, if and only if there is no higher major or minor release was already released.$ droolsjbpm-build-bootstrap/script/release/create_filemgmt_links.sh 7.6.0.Final
-
Wait 5 minutes and then check these URL's. Hit ctrl-F5 in your browser to do a hard refresh:
-
-
If it's a Final, non-hotfix release: publish the XSD file(s), by copying each XSD file to its website.
-
The Drools XSD files are at http://www.drools.org/xsd/[http://www.drools.org/xsd/]
-
Go to the https://github.com/kiegroup/droolsjbpm-knowledge/blob/master/kie-api/src/main/resources/org/kie/api/kmodule.xsd[kmodule.xsd] file (on master) and switch to the release tag.
-
Copy the raw file to https://github.com/kiegroup/drools-website/tree/master/xsd[drools-website's
xsd
directory]. -
Rename it from
kmodule.xsd
tokmodule_<major>_<minor>.xsd
so it includes its version (major and minor only, not hotfixes or quantifiers). For example for release6.3.0.Final
it is renamed tokmodule_6_3.xsd
. Do not overwrite an existing file as there should never be an existing file (because the XSD is only copied for Final, non-hotfix releases). -
Publish drools.org
-
-
Protect the new creaed branches on github against forced pushes
- https://github.com/kiegroup//settings/branches
- choose the new branch
-
Create a blog entry on the kiegroup blog
-
Include a direct link to the new and noteworthy section and to that blog entry in all other correspondence.
-
Twitter and Google+ the links.
- Most people just want to read the new and noteworthy, so link that first.
-
Mail the links to the user list.
-
-
If it's a Final, non-hotfix release:
- Notify TheServerSide and Dzone's Daily Dose.
This paragraph describes the building of a product tag
The community code repositories under the @kiegroup account contains all the code released as part of the community projects for Drools and jBPM. Every time a new minor or major version is released, a new community branch is created for that version. For instance, at the time of this writing, we have, for instance, branches master, 7.5.x, 6.5.x, etc for each minor/major version released and the master branch for future releases. Red Hat also has a mirror private repository that is used as a base for the product releases. This mirror repository contains all the code from the community repositories, plus a few product specific commits, comprising branding commits (changing names, for instance from Drools to BRMS), different icons/images, etc.
This new tag will usually be based on the HEAD of a specific community branch with the product specific commits applied on top of it.
Follows an instruction on how to do that. These instructions assume:
- You have a local clone of all Drools/jBPM repositories
- The clones have a remote repository reference to the @kiegroup repositories that we will name origin
- The clones have a remote repository reference to the @jboss-integration (> 6.5.x) or Gerrit (>7.5.x) (remote: jboss-integration OR gerrit)
Here are the steps:
1 - clone droolsjbpm-build-bootstrap repository (base branch = master or 6.5.x or 7.5.x)
$ git clone git@github.com:kiegroup/droolsjbpm-build-bootstrap.git --branch <base branch> --depth 100
2 - cd into the droolsjbpm-build-bootstrap repository
$ cd droolsjbpm-build-bootstrap
3 - Fetch the changes from the repository:
$ .script/git-all.sh fetch <remote> (i.e. remote = orgin)
4 - Rebase the corresponding branches (base branch = master or 6.5.x or 7.5.x)
$ .script/git-all.sh rebase <remote>/<base branch> <base branch> (i.e. remote = origin)
5 - Create a local branch to base the tag on. I usually name the base branch as "bsync-base branch-YYYY.MM.DD" where YYYY.MM.DD is the year, month and day when the tag is being created.
$ .script/git-all.sh checkout -b bsync-<base-branch>-YYYY.MM.DD <branch to base the tag on> (i.e. bsync-7.5.x-2017.01.15)
6 - Build local branch with product specific commits to make sure it is working. Fix any problems in case it is not working.
$ .script/mvn-all.sh -B -e -U clean install -Dfull -Drelease -Dproductized -T2 -Dgwt.memory.settings="-Xmx4g -Xms1g -Xss1M" -Dgwt.compiler.localWorkers=2
7 - Create the tag for all repositories. For product tags, we use a naming standard of "sync--YYYY.MM.DD", where YYYY.MM.DD is the date the tag is created. If for any reason more than one tag needs to be created on the same day, add a sequential counter sufix: "sync--YYYY.MM.DD.C"
$ tag=sync-<base branch>-YYYY.MM.DD (i.e. sync-7.5.x-2018.01.15)
$ commitMsg="Tagging $tag"
$ .script/git-add-remote-gerrit.sh - (adds a new remote gerrit)
ONLY for 6.5.x: .script/git-add-remote-jboss-integration.sh (add a new remote jboss-integration)
$ .script/git-all.sh tag -a $tag -m "$commitMsg" - (creates the tags)
8 - Push the tag and branches to the product server.
$ .script/git-all.sh push gerrit $tag - (pushes the tags to gerrit)
ONLY for 6.5.x: .script/git-all.sh push jboss-integration $tag - (pushes the tags to jboss-integration)