Todo 1st week:
✔ Catking development requires meeting @critical @today @3h @created(18-07-02 10:11) @started(18-07-02 10:12) @done(18-07-02 13:12) @lasted(3h)
✘ Catking requires feasibility technical interface documentation writting @high @3h @created(18-07-02 18:44) @cancelled(18-07-23 17:17)
✔ EDF time management function implement solution draft writting @high @3h @created(18-07-02 18:46) @done(18-07-08 20:37)
✔ project Vitlity webservice optimization 2018/07/05 @critical @1d @created(18-07-03 11:33) @started(18-07-05 10:15) @done(18-07-05 13:53) @lasted(3h38m)
✔ RDD employee promotions meeting 2018/07/04 @critical @1d @created(18-07-03 11:36) @done(18-07-04 16:11)
✔ presales production addon deploying 2018/07/05 @critical @4h @created(18-07-05 22:33) @started(18-07-05 21:15) @done(18-07-06 00:16) @lasted(3h)
✔ SAP HANA technical exchanges meeting 2018/07/06 @high @3h @created(18-07-05 12:06) @done(18-07-06 17:26)
Todo 2nd week:
✘ project EDF meeting 2018/07/09 @created(18-07-09 13:40) @cancelled(18-07-09 13:45)
✔ app development weekly meeting(with Pancy.Fan&Atom.Kang&Young.Yan&Zero.Zhang) @critical @2h @created(18-07-10 15:00) @done(18-07-10 17:40)
✔ RDD Employee's promotions salary increasing email sending @critical @today @created(18-07-10 17:43) @done(18-07-11 13:41)
✔ presale Oventrop development requires:batch export pdf files @critical @today @1h @created(18-07-10 17:48) @done(18-07-11 13:41)
✔ project CASIC interface meeting in company @today @created(18-07-12 16:18) @done(18-07-12 16:00)
✘ project Vitlity webservice meeting 2018/07/13 @critical @2h @created(18-07-12 17:50) @cancelled(18-07-14 15:13)
✔ project Consen development requires meeting 2018/07/13 @high @3d @created(18-07-03 11:43) @done(18-07-14 15:13)
✔ ibas web api bug fixing meeting(with Tony.Wang) @critical @1d @created(18-07-06 14:56) @done(18-08-01 10:21)
Todo 3rd week:
✘ presales project MAN interface requires meeting @high @created(18-07-09 13:49) @cancelled(18-07-14 15:53)
✔ presales Catking requires meeting 2018/07/17 @4h @created(18-07-13 10:46) @done(18-07-17 16:11)
✔ EDF Time Management 3rd party application meeting 2018/07/18 @critical @created(18-07-17 13:17) @done(18-07-18 14:50)
Todo 4th week:
✔ project Man requires evaluating 2018/07/23 @critical @created(18-07-23 15:49) @started(18-07-23 15:52) @done(18-07-27 11:12) @lasted(3d19h20m20s)
✔ project Consen development design solution 2018/07/25 @critical @2d @created(18-07-22 11:44) @done(18-07-25 22:35)
✔ project PowerVision error processing 2018/07/24 @critical @created(18-07-22 11:45) @done(18-07-24 21:54)
✔ after sales customer Talent question processing 2018/07/24 @critical @created(18-07-22 11:49) @started(18-07-26 17:12) @done(18-07-30 23:12) @lasted(4d6h)
✔ presales Excel requires evaluation meeting 2018/07/25 @created(18-07-22 11:50) @done(18-07-25 15:52)
✔ project CHEMCHINA interface bug fixing 2018/07/24 @critical @created(18-07-23 15:51) @done(18-07-29 21:53)
Todo 5th week:
✘ project Acctrue issue pull request 2018/07/29 @created(18-07-29 11:00) @cancelled(18-10-09 10:24)
✔ presales requires evaluation meeting (with Vic.Zhang) 2018/07/29 @created(18-07-29 11:04) @done(18-07-29 20:14)