Note: Please see
- BOM for required materials, beyond the actual 3D printed parts.
- Print BOM for all the required 3D printed parts for a single rack.
Slide in M3 hex nuts into the Y-bars - 4 times. Each corner should have 3 hex nuts:
Glue magnets into magnet side-modules on the Y-bars - 4 times:
Glue top and bottom magnets into side walls - 2 times:
Insert top and bottom dowel rods into side walls - 2 times:
Slide Y-bars into X-bars. Do this 2 times. You should end up with 2 trays. Orientation on the Y-bars matters here; make sure that the magnets are on the same side:
Screw together Y-bars and X-bars using 4 M3x16 FHCS screws (one screw per corner) - 2 times:
Screw in the main rails with M3x16 FHCS screws.
Prop us the side wall using the side modules. Make sure the dowels are inserted properly, and the magnets align:
Slide in the other (top) tray. Make sure the magnets and dowels align. Screw in the main rails with M3x16 FHCS screws:
Attach the top and bottom plates with 4 M3x12 screws each:
Slide in hex nuts into feet - 2 times:
Insert feet into the bottom of the rack:
Screw in feet using 4 M3x12 FHCS screws:
FIN