iSCTEP

Interpretable Security-Constrained Transmission Expansion Planning

This repository contains i-SCTEP, a tool for N-1 secure network planning that enables interpreting the value of flexibility (e.g., from energy storage systems) in terms of contributions to avoided load curtailment and total expected system cost reduction. Inspired by cooperative game theory, the tool ranks the contributions of flexibility providers and compares them against traditional line reinforcements. Specifically, the tool formulates a cooperative game among selected investment options (line reinforcements and flexibility providers) and iteratively solves a planning model to estimate the value of investments in different coalitions (combinations of investments). This information can be used by system planners to prioritise investments with higher contributions and synergistic capabilities.

At the core of i-SCTEP lies a nonlinear stochastic security-constrained optimal power flow (OPF) model developed by Mohammad Iman Alizadeh and Florin Capitanescu (Luxembourg Institute of Science and Technology) [1]. This model was improved and extended by Andrey Churkin (The University of Manchester) to include the coalitional analysis of investment options [2].

The proposed framework requires interactions between the SCTEP optimisation model and the cooperative game formulation. To elucidate these interactions, the framework diagram is presented below. The diagram is divided into three blocks corresponding to (i) the SCTEP model formulation and data preparation, (ii) coalitional analysis based on the cooperative game formulation, and (iii) output and subsequent analysis.

Framework

In the first block, the case study data and the nonlinear AC security-constrained OPF model are used to find the optimal solution to the SCTEP problem, with the objective to minimise load curtailments or to minimise the total expected system cost. The optimal solution is then analysed to perform a screening of potentially optimal investment options. That is, investments in line reinforcement and flexibility that contribute to the objectives are pre-selected for coalitional analysis. Note that if the optimal SCTEP solution identifies many investment options, e.g., more than 10 options, users are encouraged to select a limited number of investments to keep the coalitional analysis tractable.

In the second block, a cooperative game among the pre-selected investment options is formulated. That is, the set of players (investment options) and coalitions (combinations of investments) are defined. Then, to estimate the value of each coalition S, the SCTEP model is solved iteratively. At each iteration, the SCTEP model considers the set of available investment options corresponding to the set of players in coalition S, while all other investments are considered not available. Through this iterative process, the individual and combinatorial values of investments for the SCTEP problem are quantified. Once the value of each coalition in 2N is found, the marginal contributions of players to coalitions are calculated and the Shapley value is computed.

The last block of the framework includes the analysis of the calculated marginal contributions and the Shapley value for each player. This analysis ultimately allows to identify investments with the highest synergistic capabilities, i.e., the largest contributions in combination with other investments, and interpret the value of flexibility for SCTEP.

MOTIVATING EXAMPLE:

To illustrate the principles of flexibility valuation in N-1 secure network planning, the tool is applied to a simple 5-bus system with 6 lines, 3 generators, two loads and one wind farm [1]. A single-line diagram of the system is presented below:

C5 scheme

A set of 6 contingencies is considered, corresponding to the tripping of every line. The case is designed in a way that some of the post-contingency states will lead to load load curtailment. To avoid potential load curtailment, it is necessary to upgrade the system and solve the security-constrained planning problem. It is assumed that the system planner has the following investment options: 1) each line can be reinforced by a maximum additional capacity of 100 MVA, 2) flexibility (e.g., energy storage systems) can be built at bus 1 and bus 2, with a maximum capacity of 100 MW.

Using traditional network planning models, the system planner can find a single optimal solution, e.g., a cost-minimising investment portfolio. However, a single solution is not sufficient to interpret the value of flexibility in the considered planning problem. To deal with planning uncertainties, the system planner needs to prioritise the investment options and address the following questions before accepting the optimal expansion plan. How do flexibility providers contribute to avoiding potential load curtailment and reducing the total expected system cost? How effective are flexibility investments compared to line reinforcement? Which investment options jointly contribute to the defined objectives and thus have the highest synergistic capabilities in SCTEP?

To address these questions and provide additional information for the system planner, i-SCTEP tool formulates a cooperative game among the 8 investment options with 28=256 possible coalitions. For each coalition, maximum avoided load curtailment and total expected cost reduction are estimated to characterise its value. Then, the marginal contributions of players (investment options) are calculated and the Shapley value is computed to represent the weighted average contribution to all possible coalitions. The results are presented below as violin plots showing the distribution of the players' marginal contributions:

Violin plot 1 Violin plot 2

In this illustrative example, reinforcement of line 1-4 appears to be the best investment option with the highest synergistic capability, that is, the largest contributions in combination with other investments. Thus, this line should be given priority in the system expansion planning. A more detailed discussion of the results, as well as a larger case study, can be found in [2].

RUNNING THE TOOL:

The tool has been developed and tested for Julia 1.6.1 programming language with JuMP 1.11.0 and Ipopt 3.14.4 solver.

There are many components, parameters and options of the tool, as explained below. As the tool interface is not yet automated, iSCTEP users will need to set the parameters manually, define the input data, and run the corresponding .jl files.

There are two main ways to run the simulations:

  • Via "main.jl", which solves a single optimisation model, e.g., corresponding to a security-constrained OPF. This option has no coalitional analysis of investments. However, it enables a thorough analysis of a specific network operation, its costs, load curtailment, impacts of contingencies and investments, etc.
  • Via "coalitional_analysis.jl", "coalitional_analysis_UK.jl", or other dedicated scripts for coalitional analysis of specific case studies. This option requires defining N players of a cooperative game (investment options), for which a cooperative game with 2N coalitions will be considered. That is, "main_iterative.jl" will be called in a loop to estimate the value of each coalition. Then, the contributions of players to coalitions and the Shapley value are calculated.

There are several important parameters to modify the model:

  • "OPF_opt" defines the system operation problem: =0 sets a single-period security-constrained OPF model; =1 sets a multi-period OPF model.
  • "Obj_f_opt" defines the objective function: =0 sets the total system cost minimisation for a single scenario; =1 sets the minimisation of load curtailment in all scenarios and system states; =2 sets the total expected system cost minimisation for all scenarios.
  • "Inv_opt" specifies the way investment options are modelled: =0 sets investments as parameters (i.e., fixed additional capacities); =1 sets investments as variables in the optimisation model.
  • "use_trunc_coal_struct" defines the coalitions to consider in the coalitional analysis: =0 requires the full coalitional structure (2N coalitions) to be simulated; =1 sets a truncated coalitional structure (only with coalitions of one player, N players, and N-1 players).

All of the above parameters are now defined within the scripts, e.g., in "main.jl" or "coalitional_analysis.jl".

Finally, the input data and case studies are defined as follows:

  • Folder "/input data/" contains cases in ODS format and data for generating scenarios, e.g., wind power profiles. The case for simulations is then defined in the scripts, for example: filename = "input_data/C5.ods"
  • The number of scenarios is defined for each case study in the "Dimension" sheet of the .ODS files.
  • Investment costs are defined in the scripts, for example: lines_inv_cost = 5
  • The number of players (investment options), their names, capacity and location are defined in the scripts for coalitional analysis, for example: nPl = 8 # number of players pl_titles = ["L1-2" "L1-3" "L1-4" "L2-5" "L3-4" "L4-5" "F1" "F2"] if_pl_lines = [1 1 1 1 1 1 0 0] # define players: 1 = line, 0 = flexibility pl_lines_numbers = [1 2 3 4 5 6] # number of each line player pl_flex_numbers = [1 2] # bus of flexibility players pl_capacity = [100 100 100 100 100 100 100 100]
  • Finally, the tool reads data from "\data_preparation\import_WP3.json" to define available investments and load multipliers. Scripts for coalitional analysis automatically generate this JSON file for each coalition. However, if using "main.jl", users need to generate and update "\data_preparation\import_WP3.json" manually or using "\data_preparation\json_creator.jl".

The simulation results can be saved in JLD or CSV formats by activating the corresponding commands in the scripts.

At the end of the scripts for coalitional analysis, there are commands for producing and saving the plots.

REFERENCES:

[1] M. I. Alizadeh, M. Usman, and F. Capitanescu, “Envisioning security control in renewable dominated power systems through stochastic multiperiod AC security constrained optimal power flow,” International Journal of Electrical Power & Energy Systems, vol. 139, 2022

[2] A. Churkin, W. Kong, M. I. Alizadeh, F. Capitanescu, P. Mancarella, E. A. Martinez Cesena, "Interpreting the Value of Flexibility in AC Security-Constrained Transmission Expansion Planning via a Cooperative Game Framework," 2023, https://arxiv.org/abs/2310.03610

About

Interpretable Security-Constrained Transmission Expansion Planning

Resources

License

Stars

Watchers

Forks

Releases

No releases published

Packages

No packages published

Languages