Calculates the earned value of a project to indicate a diagnosis result.
Earned value management (EVM) is a project management technique for measuring project performance and progress in an objective manner by Earned value management - Wikipedia.
Add this line to your application's Gemfile:
gem 'earned_value_calculator'
And then execute:
$ bundle install
Or install it yourself as:
$ gem install earned_value_calculator
Given a project parameters, the calculator output the earned value of the project. Start date, end date, current date, budget, progress rate and actual total cost are required.
project = EarnedValueCalculator.call(Date.today - 3,
Date.today + 3,
Date.today,
100,
10,
10)
project.planned_value
#=> 50
Calculates these metrics of a project:
- earned_value
- planned_value
- schedule_variance
- actual_cost_variance
- cost_performance_index
- schedule_performance_index
- estimate_at_completion
- estimate_to_completion
- variance_at_completion
EV is calculated by multiplying %complete of each task (completed or in progress) by its planned value. It is based on the formula:
It is based on the formula:
SV = EV - PV
It is based on the formula:
CV = EV - AC
It is based on the formula:
CPI = EV ÷ AC
It is based on the formula:
SPI = EV ÷ PV
It is based on the formula:
EAC = AC + (BAC - EV) ÷ CPI = AC + ETC
It is based on the formula:
ETC = (BAC - EV) ÷ CPI = EAC - AC
It is based on the formula:
VAC = BAC - EAC
After checking out the repo, run bin/setup
to install dependencies. Then, run rake spec
to run the tests. You can also run bin/console
for an interactive prompt that will allow you to experiment.
To install this gem onto your local machine, run bundle exec rake install
. To release a new version, update the version number in version.rb
, and then run bundle exec rake release
, which will create a git tag for the version, push git commits and the created tag, and push the .gem
file to rubygems.org.
rspec spec
Bug reports and pull requests are welcome on BitBucket at https://github.com/routeflags/earned_value_calculator. This project is intended to be a safe, welcoming space for collaboration, and contributors are expected to adhere to the code of conduct.
The gem is available as open source under the terms of the MIT License.
Everyone interacting in the EarnedValueCalculator project's codebases, issue trackers, chat rooms and mailing lists is expected to follow the code of conduct.
- routeflagsinc / jma — Bitbucket
- for the Japan Meteorological Agency (気象庁) for searching new information simplifies.
- smapira / punch_time — Bitbucket
- Work time calculations using punch clock.
- smapira / rspec-css — Bitbucket
- Record your test suite's computed CSS during future test runs for deterministic and accurate tests.
- smapira/timeline_rails_helper: The TimelineRailsHelper provides a timeline_molecules_tag helper to draw a vertical time line usable with vanilla CSS.
- smapira/acts_as_tree_diagram: ActsAsTreeDiagram extends ActsAsTree to add simple function for draw tree diagram with html.
- 株式会社旗指物