Task 1 Project Management (milestone)
- Discussed draft Phase 6 scoping Google doc here
- Everyone vote by next Friday!
- We'll block 2 hours again next week for discussion
Task 9 Estimation Mode (milestone)
- Updated through atwork subtours, see estimation example setting.yaml
- Now tidying up and reconciling with other branches
- Need to update the estimation notebooks to run the estimation example
Task 3 Two Zones (milestone)
- I'm going to soon build the test example so we can get started next week